R&D Carbon has successfully completed the installation and commissioning of the anode bake furnace firing system at the Taweelah site of EMAL in Abu Dhabi. With the Phase I of the green field smelter being completed, EMAL will produce 750'000 tpa of aluminium, requiring 450'000 tpa of baked anodes. These anodes are baked in two open top furnaces.

With the installation of the latest BPS generation of R&D Carbon, outstanding performance figures could be achieved that set new standards for furnace productivity, anode quality and specific energy consumption.

A paper jointly prepared by EMAL and R&D Carbon is planned to be published at the TMS 2012 conference in Orlando.

 